# LOD LOI LOIN Concept?

**URL:** <https://community.qonic.com/t/lod-loi-loin-konzept/415>\
**Category:** Feature Requests\
**Created:** [November 10, 2026, 4:50pm UTC](https://community.qonic.com/t/lod-loi-loin-konzept/415 "2026-11-10T16:50:56Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Franz\_Madl](https://yyz1.discourse-cdn.com/flex011/user_avatar/community.qonic.com/franz_madl/32/343_2.png) [@Franz\_Madl](https://community.qonic.com/u/Franz_Madl)\
**Post date:** [November 10, 2026, 4:50pm UTC](https://community.qonic.com/t/lod-loi-loin-konzept/415/1 "2026-11-10T16:50:56Z")

</div>

Hello,

How is the support for LOD and LOI planned? Components should allow for different levels of detail internally — the same applies to LOI. Is this planned for Qonic? I know a piece of software (HiCAD by ISD) that offers the option to display details in a complex or simple manner, but for other reasons! I would wish for three levels of detail: Design / Execution Planning / Workshop Assembly Planning!

Has this even been considered before?

Kind regards,

Franz

---

<div class="post-metadata">

**Author:** ![Rodinel\_Tataru](https://yyz1.discourse-cdn.com/flex011/user_avatar/community.qonic.com/rodinel_tataru/32/8_2.png) [@Rodinel\_Tataru](https://community.qonic.com/u/Rodinel_Tataru)\
**Post date:** [November 11, 2026, 10:48am UTC](https://community.qonic.com/t/lod-loi-loin-konzept/415/2 "2026-11-11T10:48:55Z")

</div>

Hi Franz,  
Good question. Rather than fixed LOD and LOI levels, we follow the ISO 19650 way of thinking: the Level of Information Need, which describes per project and per milestone which geometry and information are needed. The information side can already be checked today: write the requirements per phase in an IDS file and check the model against it with IDS Validation ( [IDS Validation | Qonic](https://help.qonic.com/documentation/qonic-application/measure-and-quality/ids-validation) ).

Showing one component at several levels of geometric detail, e.g. for design, execution planning and workshop assembly, isn’t possible yet.